Ethereum's Glamsterdam hard fork — the network's largest upgrade since the September 2022 Merge — is on hold. On November 6, 2026, the Ethereum Foundation disclosed that auditing firm ChainSecurity had identified eight smart contract invariants that EIP-8037 and EIP-8038 would break upon activati...
"We created a repository with invariants that will be broken by Glamsterdam… contract developers, auditors, etc. [should] check their projects." — Marius van der Wijden, Ethereum Foundation Core Developer
Ethereum's Glamsterdam hard fork — the network's largest upgrade since the September 2022 Merge — is on hold. On November 6, 2026, the Ethereum Foundation disclosed that auditing firm ChainSecurity had identified eight smart contract invariants that EIP-8037 and EIP-8038 would break upon activation. The All Core Developers (ACD) call subsequently voted to postpone the Hoodi testnet fork, which had been scheduled for October 26 at epoch 132,352, until the issues are resolved. No new date has been set.
Glamsterdam bundles 12 Ethereum Improvement Proposals across the consensus layer (Gloas) and execution layer (Amsterdam). Its two headline changes — Enshrined Proposer-Builder Separation (ePBS) via EIP-7732 and Block-Level Access Lists (BALs) via EIP-7928 — would restructure how blocks are built and processed. The gas limit target rises from approximately 60 million to 200 million, roughly tripling Layer 1 throughput. But the gas repricing EIPs that make that expansion safe are the same ones now under scrutiny.
The delay does not affect work on Hegotá, the subsequent upgrade in Ethereum's roadmap. The Foundation has engaged both ChainSecurity and Dedaub for additional auditing and has asked affected developers to contact glamsterdam@ethereum.org.
Glamsterdam combines the Amsterdam execution-layer fork with the Gloas consensus-layer fork into a single coordinated upgrade. It carries 12 EIPs, the most significant of which are:
| EIP | Layer | Function | |-----|-------|----------| | EIP-7732 | Consensus | Enshrined Proposer-Builder Separation (ePBS) | | EIP-7928 | Execution | Block-Level Access Lists (BALs) | | EIP-8037 | Execution | Gas repricing for state creation | | EIP-8038 | Execution | Gas repricing for state access | | EIP-7778 | Execution | Block gas accounting without refunds | | EIP-8061 | Consensus | Increased exit and consolidation churn | | EIP-7954 | Execution | Increased maximum contract size | | EIP-7843 | Execution | SLOTNUM opcode | | EIP-7708 | Execution | ETH transfers emit a log | | EIP-7610 | Execution | Revert creation on non-empty storage | | EIP-8045 | Consensus | Exclude slashed validators from proposing |
The upgrade was originally targeted for H1 2026. Developers pushed it to Q4 2026 after scope expansion. The Sepolia testnet activated on October 6, 2026. Platåberget, a dedicated public testnet, had been running since August.
EIP-8037 adjusts the cost of creating new blockchain state. EIP-8038 adjusts the fee for accessing existing state. Together, they form the economic backbone of Glamsterdam's throughput expansion — repricing operations so the network can safely handle 200 million gas per block without state bloat spiraling.
The problem: contracts deployed today encode assumptions about gas costs. When those costs change, contracts that rely on fixed gas budgets, hardcoded gas limits, or expectations about how much gas a failed call consumes can break.
ChainSecurity published its initial analysis on October 13, 2026. By November 6, the Ethereum Foundation had cataloged eight specific invariants that Glamsterdam would violate. The Foundation created a dedicated GitHub repository with explanations, examples, and self-check prompts for developers. Specific affected projects were not named publicly, though the Foundation confirmed "a few projects" were identified as vulnerable.
The Ethereum Foundation's repository documents eight categories of contracts at risk:
Unidirectional gas consumption assumptions. Contracts that assume gas costs only move in one direction. Under EIP-8037/8038, some operations become cheaper while others become more expensive, breaking monotonic cost models.
Fixed gas allowances becoming insufficient. The most common vulnerability. Contracts that pass a hardcoded gas stipend to external calls (e.g., call{gas: 2300}) may find that stipend no longer covers the operation under new pricing.
Reverted calls returning state-creation gas. Contracts that assume a reverted external call consumes all forwarded gas. Under new rules, previously spent state-creation gas may be recoverable, allowing execution to continue past an expected failure point.
Fixed gas budgets and reserves. Contracts that maintain internal gas accounting based on current prices. This overlaps with category 2 but extends to more complex multi-step operations.
Failed-operation gas floor expectations. Contracts that check remaining gas after an external call to determine success or failure. Changed gas costs can cause these checks to produce false positives or false negatives.
Transaction failure condition assumptions. Contracts that rely on specific gas thresholds to trigger transaction-level reverts.
Off-chain infrastructure with hardcoded gas limits. Wallets, relayers, and middleware that submit transactions with fixed gas limits calculated from current pricing.
Cross-system interaction assumptions. Contracts that interact with external systems (oracles, bridges, governance modules) using gas assumptions that may no longer hold.
The Foundation's August assessment indicated most contracts would remain unaffected. The concern is concentrated on a smaller subset, but that subset could include high-value DeFi protocols and infrastructure contracts.
EIP-7732 is the centerpiece consensus-layer change. Today, Ethereum's block production runs on an out-of-protocol market: validators propose blocks, specialized builders assemble them, and trusted relays (MEV-Boost) mediate the handoff. Ethereum's protocol has no visibility into or enforcement over this process.
Under ePBS, the protocol takes over the handoff. A proposer commits to a builder's bid inside the beacon block. The builder then reveals the execution payload. Payment from builder to proposer is settled by the protocol itself.
The current relay landscape illustrates why this matters. According to October 2026 data, Ultra Sound Relay leads with 92.2% delivery share, followed by Titan at 89.1%. Flashbots' relay has declined from historical dominance to 1.7% of market share. But builder concentration is more severe: Titan and Quasar produced 73% of all MEV-Boost blocks in October 2026, up from approximately 60% a year earlier. Titan alone built 52.4%.
ePBS does not solve builder concentration — exclusive order flow deals, private mempools, and algorithmic advantages persist. What it does is eliminate relays as a censorship chokepoint and infrastructure dependency. The relay operators — Flashbots, Ultra Sound, Titan, Aestus — lose their intermediary role. Estimates suggest MEV extraction losses could fall by up to 70%.
A separate pre-Glamsterdam bug was patched in late October 2026: developers discovered a flaw that could have allowed an operator to redirect ETH intended for new validator deposits to builders. The fix was merged before the Hoodi testnet was scheduled to activate.
EIP-7928 introduces enforced block-level access lists (BALs). These lists record the accounts and storage locations accessed during a block, together with post-transaction state changes. The mechanism enables three capabilities:
BALs are a precondition for raising the gas limit. Without parallel processing, a 200 million gas block would take too long for nodes to validate within the 12-second slot time.
EIP-7778 complements BALs by changing how gas refunds interact with block accounting. Storage-clearing refunds still reduce what a transaction pays, but they no longer shrink the transaction's footprint in block-level gas accounting. This prevents blocks from packing more real execution work than their stated limit implies.
Ethereum.org describes 200 million as the gas limit floor that Glamsterdam enables, with developers testing against a 150 million reference during the Sepolia run.
As of October 2026, approximately 43.7 million ETH is staked across roughly 868,000 validators — 35.8% of circulating supply. This is near the all-time high of 33.98% recorded in August 2026 (the difference reflects ETH supply changes and measurement timing).
EIP-8061 restructures exit and consolidation churn limits:
The practical impact: exit queues that stretched beyond 40 days during peak demand in 2025 would clear significantly faster. Institutional stakers, particularly those managing large positions across multiple validators, gain material improvement in liquidity timing.
EIP-8045 excludes slashed validators from the proposer rotation, a smaller change but one that removes a potential attack surface where a slashed validator could still propose a malicious block during its remaining active period.
Before the November 6 halt, Glamsterdam had completed several testnet milestones:
The Hoodi testnet fork, which would have been the final rehearsal before mainnet, was scheduled for October 26 at epoch 132,352. It was this fork that ACD postponed on November 6.
Glamsterdam's calldata repricing EIPs and higher gas limit directly affect Layer 2 rollups that post data to Ethereum. Lower calldata costs reduce L2 settlement expenses. Estimates project L2 settlement costs falling by approximately 70%, which would intensify fee competition among major L2s including Arbitrum, Optimism, and Base.
The L1 fee reduction is projected at approximately 78.6% for users transacting directly on Ethereum. Combined with blob data improvements from the prior Pectra and Fusaka upgrades, Ethereum's data availability layer becomes substantially cheaper for rollups — though whether those savings pass through to end users depends on L2 operator pricing decisions.
Glamsterdam represents the most comprehensive restructuring of Ethereum's economic and consensus machinery since the Merge. It moves block production on-chain, enables parallel processing, triples the gas limit, and overhauls validator exit economics. The scope alone explains why it has been delayed twice — first from H1 to Q4 2026, and now indefinitely pending resolution of the gas repricing risks.
The November 6 pause is a function of Ethereum's upgrade governance working as designed: ChainSecurity identified real risks in testnet, the Foundation published them transparently, and ACD halted the process before those risks could reach mainnet. Whether the resolution takes weeks or months depends on how many deployed contracts rely on the eight broken invariants and whether EIP-8037/8038 can be modified without undermining the gas limit expansion they enable.
For the 868,000 validators, the L2 ecosystem settling data on Ethereum, and the protocols operating within the current MEV-Boost relay system, Glamsterdam's arrival is a question of when, not if. The economic incentives — lower fees, faster exits, protocol-level block production — are too large to abandon. The question is whether the transition can be made without breaking what is already deployed.